Dates and scheduling

You write only the dates you know: a fixed start here, a duration and a dependency there. Facet computes the rest (every node’s start and end, which tasks are late, the critical path) and shows it in the views. Computed dates are never written back to the file.

# Station roll-out
start:: 2027-04-05
- [ ] Site survey [id:: survey] [duration:: 1 week]
- [ ] Order docks [id:: docks] [after:: !survey] [duration:: 3 weeks]
- [ ] Install docks [id:: install] [after:: !docks + 2 days]
duration:: 10 days
- Pilot opens [type:: milestone] [after:: !install] [due:: 2027-05-31]

The survey starts with its parent on 5 April and lasts a week. Ordering starts when the survey ends, installing two days after the order ends, and the milestone sits at the end of the installation. If that end passes 31 May, the milestone is late.

Dates appear only in properties (start::, end::, due::, last::, away::), never at the start of a line.

Form Example Covers
year 2027 the whole year
month 2027-06 the whole month
day 2027-06-10 the whole day
date and time 2027-06-10T09:30 that minute
with seconds 2027-06-10T09:30:15 that second
today today the current day
Markwhen date June 2027, 1/5/2027, 5 Jan 2027 9am its precision
  • ISO dates are written YYYY, YYYY-MM, YYYY-MM-DD, then optionally THH:mm and :ss. Other forms are read with Markwhen’s date grammar, as long as they name a single date (a year, a month, a day or a time).
  • Time zones are not supported (2027-06-10T09:30Z is an error); dates are local, without zone.
  • A date that names a range (2027-06-10/2027-06-12), a relative phrase such as next friday, or an !id is not a date. To start after another node, use after::.
  • A date that cannot be read is a bad-date error.

A date stands for its whole precision:

  • start:: 2027-06 starts on 1 June and end:: 2027-06 ends with 30 June.
  • A date-only end is inclusive: end:: 2027-06-10 includes all of 10 June.
  • A date and time is a point: end:: 2027-06-10T17:00 ends at 17:00.

duration:: is one positive whole number and a unit:

Unit Spellings
minutes m, min, minute, minutes
hours h, hour, hours
days d, day, days
weeks w, week, weeks
months month, months
years y, year, years

A space between number and unit is optional: 4h, 3 days, 2 w. Fractions (1.5 days) and zero are errors (bad-duration).

Durations add calendar time. There are no working-day calendars and no holidays: 2 business days or 5 working days is a bad-duration error. Months and years follow the calendar: 1 month from 31 January ends on the last day of February.

after:: makes a node start when other nodes end (finish to start).

- [ ] Paint the docks [after:: !install]
- [ ] Open to the public [after:: !paint + 3 days, !permit]
  • Each entry is !id, optionally followed by an offset: !id + 2 days. The offset is a duration.
  • Several entries are comma-separated. The node starts at the latest end among them, offsets included.
  • Targets must be tasks, events, milestones or groups. A note, requirement, file, folder or repeating task is a bad-after-target error. An id that does not exist is an unknown-id error.
  • Only after:: creates scheduling links. An !id in a title or description is a link to navigate, never a dependency.
  • Cycles are dependency-cycle errors, including cycles through a parent: a child that comes after:: its own roll-up parent.

Facet computes a start and an end for every node it can. A node’s start comes from the first of these that applies:

  1. its fixed start::;
  2. its end:: minus its duration::;
  3. its after:: dependencies: the latest target end plus offset;
  4. with only a duration::: the start of its nearest anchored ancestor (see Unanchored nodes).

Its end comes from its fixed end::, else its start plus duration::.

So start::, or end:: with duration::, wins over after::. Whatever is still missing comes from the node’s children (see Roll-up), never giving an end before the start.

A leaf node with a start but nothing that gives an end lasts the date it was given: start:: 2027-06-10 alone lasts that day, start:: 2027-06 the whole month, and start:: 2027-06-10T09:30 is a point. A leaf with only after:: starts and ends at the end of its targets.

If a node’s start (fixed or from after::) is past its own fixed end::, lint warns end-before-start and the node has zero length at its start.

A node with a duration:: but no start::, no end:: and no after:: is unanchored. It starts at the start of its nearest ancestor that has a start of its own: fixed, from after::, or itself unanchored and placed. A start that a parent only rolls up from its children does not count.

# Workshop week
start:: 2027-09-06
- [ ] Prepare tools [duration:: 2 days]

Without such an ancestor the node is unscheduled: the Gantt shows it in an “unscheduled” lane, and lint warns unscheduled on tasks. A task that already has an error that prevents scheduling (an unknown or bad after:: target, a dependency cycle, a bad date or duration) does not also raise unscheduled, nor does a task waiting on an unscheduled one.

Milestones have zero length. A milestone sits at its start::, else at the end of its after:: targets, else, with neither, on its due:: day.

A parent with dates of its own (a start and an end of its own, for example start:: and duration::) is a box: its children are scheduled inside it.

- [ ] Festival stand [start:: 2027-07-02] [end:: 2027-07-04]
- [ ] Set up [id:: setup] [duration:: 1 day]
- [ ] Demo rides [after:: !setup] [duration:: 2 days]
  • An after:: inside a box never starts before the box starts.
  • A child that starts before or ends after its box gets a children-outside-parent warning.
  • So does a child that starts before a parent’s own start, or ends after its own end, when the parent has only one of them.

A parent without its own dates is pure roll-up:

  • its span runs from its children’s earliest start to their latest end;
  • its progress is its children’s progress weighted by their duration (a plain average when none has a duration);
  • its state is rolled up from its tasks, see States.

Cancelled children do not count for any of these. A parent with only one own date (a start:: or an end::) takes the missing side from its children.

due:: is a deadline, not a scheduling date; it is mostly used on milestones. If a node’s computed end passes the end of its due:: date, the node is late: red in the Gantt and a late warning. Done, cancelled and repeating tasks are never late.

The critical path of what a view shows (a file, a folder, an included node) is the chain of after:: dependencies and anchors that sets its end. The Gantt highlights it; see the Gantt view.

Repeating tasks have no bar and take no part in scheduling. Their next occurrence is shown instead, see Repeating tasks.

Computed dates are shown in views and returned by the CLI, but never written to the file. Only an explicit change writes dates: dragging a bar in the Gantt writes fixed dates in the form the node already uses, as described in How Facet writes.

facet schedule <dir> prints the computed dates of a workspace, one line per node with dates, a repeat or a scheduling problem. For the example at the top of this page, with a weekly task in another file:

pilot/stations.md:1:3: 2027-04-05..2027-05-14 Station roll-out critical
pilot/stations.md:4:7: 2027-04-05..2027-04-11 Site survey critical
pilot/stations.md:5:7: 2027-04-12..2027-05-02 Order docks critical
pilot/stations.md:6:7: 2027-05-05..2027-05-14 Install docks critical
pilot/stations.md:8:3: 2027-05-15 Pilot opens milestone critical
team.md:2:7: next 2027-04-12 Clean the docks
5 scheduled, 0 unscheduled

Each line is path:line:column: when title flags.

when Meaning
start..end the span, end inclusive
one date a single day, or a milestone
next <date> the next occurrence of a repeating task
unscheduled no start and no anchored ancestor
undated (error) a bad value or after:: target
undated (cycle) the node is in a dependency cycle
undated (waiting) an after:: target or its anchor has no dates
Flag Meaning
milestone zero length
box the node has its own start and end, and children
critical on the critical path of the node’s file or folder
late (due <date>) the computed end passes due::

The last line counts scheduled and unscheduled nodes. The command takes --today YYYY-MM-DD to compute as of another day. See also Lint and querying with the CLI.